288 core fibre being run to the node at Flagstaff Street, starting up from Bateman Street then to Learmonth Drive, then to Flagstaff Street. I got the boys
The physical node is expected to be finished on 14 December 2017. UPDATE: Node had power connected and physical installation completed 15 December. The Ready For Service (RFS)
Workmen have started installing conduit on Flagstaff Street to link the CMUX at the end of Learmonth Drive to the node site on the corner of Flagstaff Street
Fibre To The Node (FTTN) work is starting in Kambah! (as opposed to Fibre To The Premises which the project’s goal) This however, is a key milestone in
Hi, Most of you would have received a flyer in their letterbox addressed to Gleneagles Residents, regarding the NBN. I have had a number of residents bring this
For your information, NBN’s contractors have started the process of ‘rodding and roping’ – whereby pull rope is installed between pits/pillars which will allow them to drag fibre through
Welcome to our new sign ups to for the Gleneagles Estate FTTP Project. Your participation in this project makes NBN cheaper for all participating. Make sure you let
Changes to Estimator Costs After obtaining some maps which indicate Telstra cable runs, some adjustments have been made to how calculations are made for residents in DA71. This
What you need to do now: Go to http://www.gleneaglesestate.net and register on the website under “Register/Your info”. If you have already registered, it is essential that you update
The committee has had progress in negotiations with NBN, benefits of which will be made available to residents who register with the project. They are fully supportive of the