288 core fibre being run to the node at Flagstaff Street, starting up from Bateman Street then to Learmonth Drive, then to Flagstaff Street. I got the boys
The physical node is expected to be finished on 14 December 2017. UPDATE: Node had power connected and physical installation completed 15 December. The Ready For Service (RFS)
Workmen have started installing conduit on Flagstaff Street to link the CMUX at the end of Learmonth Drive to the node site on the corner of Flagstaff Street