NBNCo contractors have begun replacing pits in Stage 2 of the Estate as part of the FTTP process. Lead In Conduits were cleared as well by contractors engaged
The process of inserting drawstrings between pits to pull fibre through has commenced for the trial group of Technology Choice Individual Premises Grouped Applicants. This is a great
With the payment of the total build cost invoice completed for the trial group, “Gleneagles Estate Stage 2” grouped applications are now open. “Stage 2” of Gleneagles Estate consists
The trial group of 9 residences (aka. “Test Bunnies”) from “Stage 2” of Gleneagles Estate have signed their contracts on Friday 11 January 2019 for the Grouped Individual
Copper remediation has commenced this week in Stage 2 of the Estate. You should have received notification from your RSP about this work, which involves replacing all the
Hi An update on the copper remediation work in the estate form NBNCo: As you are aware the field team have been completing on going remediation work within
The work the committee has done over the last 4 years has provided returns to the community, with responsive action by NBNCo undertaken with the implementation of remediation
ABC is reporting on the difficult journey towards getting a grouped FTTP NBN connection. …Once they committed, the process was very quick. The build commenced in late February
As a result of the 15 premises who reported issues with their connection through the Gleneagles Estate FTTP Committee, capital works are well underway by NBNCo. Thank you